"how many EV charging stations has NEVI installed? After all, the NEVI program was enacted in November 2021. The Biden administration was hoping to have 500,000 charging ports
installed by 2030. With $5 billion allocated over a five-year period,
one would think that NEVI would have established a well-functioning
network of EV chargers by now. Here are some estimates as to how many EV
chargers have been installed under NEVI:
· The EV States Clearinghouse, which is co-maintained by the
National Association of State Energy Officials and the American
Association of State Highway and Transportation Officials, has the estimate at 532 charging ports currently open.
· An industry analysis reported that EV charging data analytics company Paren puts the estimate at 725 ports.
· The Government Accountability Office calculated that
as of April 2025, there were 384 EV charging ports installed under
federal government programs. Notably, this figure includes ports from
NEVI and another program called the Charging and Fueling Infrastructure
Grant Program.
Regardless of the estimate used, the number of charging ports
installed by the federal government is less than 1,000 and accounts for
much less than one percent of the 235,428 charging ports available as of January 2026
and the 500,000 charging ports promised by the Biden administration by
2030. More than four years after enactment, and with billions
appropriated, this level of deployment suggests more than ordinary
implementation lag. Even a backloaded program would show clearer signs
of growth by this point. Instead, NEVI’s output indicates structural
bottlenecks embedded in its design rather than temporary startup delays.
Paperwork over power
Even before the Trump administration decided to
rescind the existing NEVI Formula Program Guidance and suspend state
approvals of deployment plans, NEVI was already floundering in red tape.
As of February 6, 2025,
which was a few days after USDOT Secretary Sean Duffy was sworn into
office, $2.7 billion of the $3.3 billion available in NEVI funds were
unobligated. In plain terms, most of the money Congress set aside had
not been committed to projects.
According to the center-left think tank Third Way,
NEVI’s slow progress is not due to lack of need or funding, but to
bureaucratic hurdles. Complex requirements and delayed federal guidance
left states navigating red tape instead of building charging stations,
highlighting inefficiencies in the program’s design.
The Environmental Law Institute further breaks down
these hurdles mentioned by Third Way by showing that NEVI’s deployment
delays are baked into the program’s structure. States and contractors
must navigate local building approvals, utility interconnection studies,
and environmental reviews for each proposed site, which often stalls
projects for months before a single charger goes live.
In addition, federal “Buy America” requirements add supply-chain
constraints that create additional bottlenecks and increases production
costs. Industry groups and state Departments of Transportation
have warned that “Buy America” requirements could delay federal EV
infrastructure projects due to limited domestic suppliers and complex
compliance processes. These intertwined requirements illustrate how
well-intentioned federal oversight can transform a supposedly
fast-moving infrastructure program into a slow-moving bureaucratic
behemoth.
Private sector vs. NEVI deployment timelines
An interesting point of comparison is the project timelines between
the private sector and NEVI installations. Industry analysis indicates
that regulatory and utility interconnection processes alone commonly add
a year to 18 months
to the timeline for NEVI‑funded charging projects, well before
construction begins. Although all 50 states have submitted and received
approval for NEVI EV charging deployment plans, the plans do not include
uniform benchmarks for how long it takes from award to station
operation. Arizona expected it to take a year to install once approved, whereas California provides a range of one to two years.
By contrast, the private sector reports shorter timelines. EV
charging financing company Sustainable Capital Finance (SCF) estimates
that it can take 3 to 16 months to install an EV charger, whereas EV charging company EVgo puts the figure at 18 months.
EV charging stations take time to install, irrespective of red tape. At
the same time, these diverging timelines illustrate why the private
sector is able to generate tens of thousands of ports in the time that
NEVI has installed fewer than 1,000 ports.
Daren Bakst, director of CEI’s Center for Energy and Environment, has noted
this discrepancy reflects a broader principle: states and private
actors ultimately determine where and when chargers are built, and
government mandates cannot substitute for market-driven deployment. In
fact, Bakst highlighted that even with billions allocated to NEVI, no
chargers had yet been installed at the time of his analysis in December
2023. This insight reinforces the idea that federal intervention cannot
reliably accelerate infrastructure deployment.
Beyond regulatory red tape, NEVI has been hampered by predictable
governance failures that exacerbate the timeline issues. For example, a
federal court recently ruled that
the US Department of Transportation unlawfully froze congressionally
appropriated NEVI funds, which forced states to litigate simply to
access money already authorized by law. Such administrative paralysis is
not an anomaly. It is a predictable outcome when a program centralizes
decision-making in federal agencies subject to shifting priorities,
complex compliance rules, and political interference.
NEVI spending fails the traveler
Despite a $5 billion commitment made in 2021 to build a nationwide EV
charging network, there are fewer than 1,000 operational charging
ports. This amount represents a miniscule fraction of the ports already
available nationwide, and more importantly, the amount promised by the
Biden administration. The Government Accountability Office highlights how
NEVI lacks clear performance goals or benchmarks, meaning policymakers
cannot even track whether NEVI is meeting its intended outcomes.
Combined with bureaucratic hurdles, slow deployment, and small scale of
charging ports at this stage, it becomes difficult to argue that NEVI is
doing anything of substance to positively contribute to transportation
infrastructure.
At the same time, private companies continue to expand the EV
charging network across the US and often complete projects in a matter
of months instead of years. History has shown that building a nationwide
network of fueling infrastructure does not require subsidies. Gas
stations achieved this growth organically in the 20th century without subsidies. Those same market forces can drive and already have been driving EV charger deployment."